Why oxygen equipment falls idle.
Most equipment lacked maintenance
In 2022 the Ministry of Health, with support from GHSC-PSM and CHAI, concluded a national oxygen assessment. The roadmap says most oxygen equipment suffered from a lack of maintenance and was non-functional, obsolete or running below par, and that recent donations had made the situation worse.
Few trained technicians
At the time of the assessment, only three technicians in the country had received training, during the installation of one PSA unit at Quelimane General Hospital, the roadmap says. The Ministry’s infrastructure and hospital equipment department, DIEH, has about 200 maintenance technicians nationwide.
Service agreements that end
The Monapo and Mocuba plants had two-year service agreements, funded by USAID, from the arrival of the equipment. The roadmap says the Ministry needs a budget for maintenance once they end, and that it was seeking an outside provider to service the other PSA plants.
Courses online
GHSC-PSM created three courses, one on operating and maintaining PSA plants, and adapted them with Jhpiego for the Ministry’s Telesaúde portal. Learners receive a certificate when they complete a module.